| Title Of the Project |
Project Start Year |
Project End Year |
| ROUGHNESS MEASUREMENTS AND TRAVEL TIME STUDIES ON INDORE - DEWAS SECTION OF NH-3 |
1999 |
2000 |
| DESIGN OF RIGID PAVEMENT AT JALLANDAR TERMINAL OF IOC |
1999 |
2000 |
| DESIGN OF RIGID PAVEMENT AT MAGHALSARAI TERMINAL OF INDIAN OIL CORPORATION |
1999 |
2000 |
| UPDATION OF ROAD USER STUDY DATA AND ROAD USER COSTS |
1999 |
2003 |
| TO CHECK THE COMPACTION OF SUBGRADE OF DIVERSION ROAD TO FLYOVER ON NH-24, NOIDA ROAD |
1999 |
2000 |
| SUPERVISION MISSION UNDER ANDHRA PRADESH ECONOMIC RESTRUCTURING PROJECT |
1999 |
2000 |
| QUALITY CONTROL OF BITUMINOUS BASE & WEARING COURSE OF ROAD SECTION UNDER PWD, NCT, DELHI. MADHUBAN CHOWK TO MUKERBA CHOWK 4.3 KM 6 LANE WIDE |
1999 |
2000 |
| QUALITY CHECK OF BITUMINOUS BASE AND WEARING COURSE OF ROAD SECTION UNDER PWD NCT DELHI NH-1 KM TO 16 TO KM 23, 9.5 M WIDE |
1999 |
2000 |
| INVESTIGATION FOR CAUSES OF DISTRESS AND SUGGEST REMEDIAL MEASURES FOR IMPROVEMENT & STRENGTHENING OF C-HEXAZON, NDMC |
1999 |
2000 |
| ADVISORY INSPECTION OF RUNWAY AT NAVAL AIR STATION AT GOA AND TO ADVISE IMPROVMENT MEASURES |
1999 |
2000 |
| FEASIBILITY STUDY ON FLYASH OF PANKI THERMAL POWER STATION PANKI, KANPUR FOR ITS USE IN ROADS AND/OR EMBANKMENTS |
1999 |
2000 |
| EVALUATION OF LAB POLISHED STONE VALUE OF SOME SELECTED AGGREGATE SAMPLES FROM DURGAPUR & PANCHMI |
1999 |
2000 |
| STANDARDISATOIN STUDY OF ROMDAS BUMP INTEGATOR |
1999 |
2000 |
| QUALITY CONTROL CHECKS OF BITUMI- NOUS BASE AND WEARING COURSE OF WIDENING AND STRENGTHENING, ROHTAK ROAD NH-10, 4.8 KM, 3 LANE |
1999 |
2000 |
| QUALITY CONTROL CHECKS OF BITUMIN- OUS BASE AND WEARING COURSE OF WIDENING AND STRENGTHENING, NAJAF- GARH TO PEERAGARHI 5 KM 6 LANE |
1999 |
2000 |